Restoration and Modernisation
By the 1950s, the material state of 10 Downing Street had reached crisis point. Bomb damage had worsened existing structural problems: the building was suffering from subsidence, sloping walls, twisting door frames and an enormous annual repair bill.
The Ministry of Works carried out a survey in 1954 into the state of the structure. The report bounced from Winston Churchill (1951–1955) to Anthony Eden (1955–1957) to Harold Macmillan (1957–1963) as one Prime Minister followed the other. Finally, a committee set up by Macmillan concluded that drastic action was required before the building fell or burnt down.
They put forward a range of options, including the complete demolition of Number 10, 11 and 12 and their replacement with a new building. That idea was rejected and instead it was decided that Number 12 should be rebuilt, and that Numbers 10 and 11 should be strengthened and their historic features preserved.
The architect Raymond Erith was selected to supervise the work, which was expected to take two years and cost £500,000. It ended up taking a year longer than planned and costing double the original estimate. The foundations proved to be so rotten that concrete underpinning was required on a massive scale.
Number 10 was completely gutted. Walls, floors and even the columns in the Cabinet Room and Pillared Room proved to be rotten and had to be replaced. New features were added too, including a room facing onto Downing Street and a veranda at Number 11 for the Chancellor.
It was also discovered that the familiar exterior façade was not black at all but yellow. The blackened colour was a product of two centuries of severe pollution. To keep the familiar appearance, the newly cleaned yellow bricks were painted black to match their previous colour. Erith’s work was completed in 1963, but not long afterwards, dry rot became apparent and further repairs had to be undertaken.
Margaret Thatcher (1979–1990) appointed architect Quinlan Terry to refurbish the state drawing rooms at the end of the 1980s. Two of the rooms, the White Drawing Room and Terracotta Room, gained ornate plasterwork ceilings. In the White Drawing Room, this included adding the national emblems of England, Northern Ireland, Scotland and Wales.
All the building work of the past few decades could have been ruined when a terrorist bomb exploded in 1991. An IRA mortar bomb was fired from a white transit van in Whitehall and exploded in the garden of Number 10, only a few metres away from where Prime Minister John Major (1990–1997) was chairing a Cabinet meeting to discuss the imminent Gulf War.
Although no one was killed, it left a crater in the Number 10 gardens and blew in the windows of neighbouring houses. John Major and some of his staff moved into Admiralty Arch while damage caused by the bomb was repaired.
By 2006, it was clear that the Downing Street complex was no longer able to support the business of the Prime Minister’s Office reliably. Independent surveys established that the building was no longer weather-tight, the heating system was failing, and the ICT network was at the limits of its operation. Power outages and water leaks were frequent occurrences and impacted significantly on the day-to-day operation of the Prime Minister’s Office.
In addition to deterioration through age, pressures on the buildings had increased dramatically over recent years, through an increase in occupancy (stable at around 50 for many years) to around 170. In 2006, Prime Minister Tony Blair (1997–2007) authorised a new programme of improvements, with the building remaining operational throughout. Work was launched to address structural failure, renew the infrastructure, improve access and enhance the building’s sustainability.
Structural issues were among the first to be tackled, and a phased exterior repair project was launched to address failing lead guttering, cracking brickwork and other structural issues. The distinctive black colourwash was also renewed, as it had faded away in many areas to reveal the yellow brickwork beneath. During the course of the works it was discovered that the façade of 11 Downing Street was unstable, and had to be secured using 225 stainless steel pins. All work was carried out in consultation with English Heritage.
Other projects have been undertaken to renew the building’s ageing infrastructure and to replace many of the building’s key services, including heating, fire protection and electrical power distribution. Sustainability is a key feature of the programme and a 10% reduction in carbon emissions was realised during 2011. Rainwater harvesting was introduced in 2009, providing a sustainable source of water for the garden. Accessibility for disabled visitors has been significantly improved through the introduction of ramps and modernisation of lifts. Many of the public areas of the building have also been restored, including the front entrance hall, the state and small dining rooms and the study.
An ongoing programme is in place to upgrade facilities to modern standards, and to ensure the preservation of this historic building for years to come.